Here's the swimming pool timeline update

Bid accepted in February and awarded in March

Here are the plans for the swimming pool renovations to take place next fall:
* A splash pool will be installed just south of the current pool; splash pools are popular now and being added to pools in villages and large cities.
* The bathhouse will be renovated.
* A new concession stand will be built.
* A new filtration system will be built on the north side of the bathhouse.
* Concrete around the pool will be replaced.
The pool itself will be unchanged.

––Here's the timeline: the Village will accept bids in February and award bids in March. Work will begin after the pool closes for the 2017 season in September.