Here's the 2019 Ada street projects list
The village of Ada is accepting bids for its 2019 street projects, according to Jami Hall, village administrator.
Bids are due at noon, Friday, June 28, and will be opened at that time in the village municipal building. The village has placed an Oct. 31, 2019, deadline on all projects
A map at the bottom of this story shows the project areas.
This year’s projects include:
Alleys – mill and compact
• North Johnson to North Simon between East Buckeye and East Highland
• East Highland to East Montford between Johnson and Simon
Streets – 2-inch blacktop overlay
• North Simon from Franklin North to end
• Montford from Main to Gilbert
• Gilbert from Buckeye to Montford
• Grand from Buckeye to Montford
• Conley from Grand to end of street
• Ream from Lincoln to University
• Lehr from Ream to end of street
• College from Main to Johnson
Hall said that, in general, the project consists of pavement asphalt overlay, milling and alley repair.
Stories Posted This Week
Friday, August 7, 2026
Thursday, August 6, 2026
Wednesday, August 5, 2026
Tuesday, August 4, 2026
Monday, August 3, 2026
- Ada will celebrate National Night Out on Aug. 5
- Michael E. Bailey worked for Bartlett Roofing
- USV Local Schools announce free or reduced price meal program for 2026-2027
- Need for blood donations continues during blood and platelet shortage
- Moved: APL book group discussion is August 11
- Learn about Ada Schools booster groups
- Save Oct. 3 for Irish Iron Swap Meet