Willeke Phase II assessments total $193,500
The assessment process for the now-completed Willeke Avenue Phase II project is Ada council’s Tuesday’s agenda.
That project involved 30 property owners along Willeke, South Johnson Street and South Simon Street. It included installation of new water and sanitary sewer lines, road improvement, curbs, gutters and sidewalks.
Phase II’s total cost was $1,025,311. The assessment on the project is $60 per project foot. The assessment total is $193,500, according to Jamie Hall, village administrator.
Property owners have three options for payment:
• Pay in full by Nov. 1
• Make a partial payment by Nov. 1 and have the remaining balance placed on the owner’s property tax assessment
• Stretch the payments over 20 years at 4.75 percent on the owners’ property tax assessment.
Property owners also have the option of making a partial or complete payment later. Council’s agenda is attached below.
Tuesday's meeting is available via WebEx. The WebEx access information is:
Meeting link: https://adaoh.webex.com/adaoh/j.php?MTID=m2f5d905ba038ee991d58f5d152952b...
Meeting number: 129 384 7606
Stories Posted This Week
Sunday, June 28, 2026
Saturday, June 27, 2026
Friday, June 26, 2026
Thursday, June 25, 2026
Wednesday, June 24, 2026
- Bluffton Icon headlines, June 24
- Luvu a Latte temporary closure until July 14
- County Line Church celebrates 140 years with Birthday Bash
- Blueberry fundraiser supports Ada Schools music programs
- Community invitation to Coffee with the Sheriff
- Results of Icon poll: How connected do you feel to the Ada community?
- Loving Laura’s Curls created to provide wigs for local cancer patients
- Ada Gators felled by Wapak
- Coressel kicks off campaign to represent 83rd district in Ohio Statehouse