County Road 75 bridge replacement near Ada
ODOT District 1 has announced that bridge replacement on County Road 75 between Township Road 30 and State Route 81 over Hog Creek will detour traffic until October 2023. Access to properties will be maintained. (ODOT MAP.)
Project schedule
- Construction begins: June 2023
- Construction ends: October 2023
Traffic impacts
Vehicular traffic will be detoured. Access to all properties will be maintained throughout construction.
Work at this location will occur in a regulated floodplain. Impacts to this floodplain are anticipated to be minor and result in no rise in localized flood levels. A statement of findings detailing the results of the final floodplain analysis will be made available and posted to this webpage: Environmental Documents and Project Location Maps
Stories Posted This Week
Saturday, July 18, 2026
Friday, July 17, 2026
Thursday, July 16, 2026
- Norma Mathews Wilhelm was an elementary school teacher and homemaker
- July 27 blood drive at Ada Community Visiting Nurses
- Alger Public Library BBQ fundraiser tickets on sale
- July 18 Dog Days of Summer event in Kenton
- New communication platform adopted by Ada Schools
- Cancer screening in women: Recommendations, trends, and solutions
Wednesday, July 15, 2026
- Ohio EPA issues Air Quality Advisory due to Canadian wildfires
- UPDATE July 15 boil water advisory lifted for 700-800 blocks of S. Johnson St.
- Murder trial of Donna Jo Miller postponed until December
- June 2026 Hardin County rainfall reports
- Sept. 22-24 Farm Science tickets on sale
- Beatitudes serves 136 meals on 4th of July