Weather expected to impact Sept. 27 street paving
The Village of Ada has announced that the Street Maintenance Project schedule is weather dependent. For Friday, Sept. 27, pavers will continue working in Ada as able, starting on South Park Drive.
If work is delayed by rain, two paving crews will work on Saturday. One crew would work on Pebble court (finish coat), and then move to north Johnson. The other crew will work in the downtown alleys.
Completed to date: Oak Street, Lehr, Ballard.
Remaining paving: South Park, Downtown alleys, North Johnson.
From the Village: "Thanks for your cooperation and understanding through the project construction."
Stories Posted This Week
Friday, May 23, 2025
Thursday, May 22, 2025
- Are microplastics a potential risk for cardiovascular disease?
- ONU sports roundup, May 14-20
- Floyd L. Cleveland was a U.S. Army veteran
- Ada softball camp for grades 7-12 debuts in June
- Bulldog Williams ousted at district tennis tourney
- Eagle Scout project going up at War Memorial Park
- 65th anniversary to be celebrated by Paul and Nancy Oestreich
Wednesday, May 21, 2025
Tuesday, May 20, 2025
- Vote for Ada Schools in Paint the Plow ODOT competition
- Dennis “Denny” Eugene Covault worked for the Lima Refinery
- Roundhead man arrested in child pornography investigation
- Community champions celebrated by United Way of Hardin County
- 2025 Wes Davis Memorial Scholarships awarded
- Ada Bulldog softball blanks Grove in district semis
- West Montford Ave. work: everything but the street