Ada street projects, farmland lease moving along
Several 2019 Ada village projects are moving along this month. They include two street project and one lease of tillable farm land in the village. Details follow:
• The Ream Street 2019 phase II reconstruction and water replacement project, estimated to cost $712,560, is in the bid stage. Bids will be opened on Tuesday, Feb. 5.
The project consists of installation of a storm sewer, storm sewer laterals, repair of existing sanitary sewer laterals and water service branches if needed, curb ramps, barrier curb, and pavement planing along South Simon Street, South Johnson Street and East University Avenue.
Attached to this story are bid specs for the project.
• The Willeke Avenue phase II reconstruction project bid results will be available on Wednesday, Jan. 30, on Choice One Engineering website.
The bid openings for that project took place on Jan. 29.
• The village property, which includes 33 tillable acres of farm ground in the Grass Run Industrial Park area, is also in the bid stage for leasing.
A two-year lease for the farm land begins March 1, 2019, and ends Feb. 28, 2021. Bids will be opened at 10 a.m., Friday, Feb. 15.
Attached to this story are specs on that lease.
Click on the illustrations to enlarge. For a printer-friendly copy, open the attachments below the illustrations.
Stories Posted This Week
Tuesday, July 29, 2025
Monday, July 28, 2025
Saturday, July 26, 2025
Friday, July 25, 2025
- Special board of education meeting on July 29
- SR81 at Thayer roundabout construction, bridge replacement
- Sondra May Amstutz worked for Airfoil Textron and Midbus
- Jeffrey A. Hunt taught and coached at area schools
- Larry J. Marsh worked for Precision Strip
- Minutes of July 21 Liberty Twp. Park District public meeting
- Old Route 69 Brewery to open on August 1
- Freed Center subscriptions available August 4