U.S. 30 Slabtown bridge estimated to take 60 days to repair
The Ohio Department of Transportation (ODOT) and the Allen County Engineer's Office have completed the initial scope for the repair of the Slabtown Road bridge over U.S. 30, which closed in December due to a bridge strike.
The tentative schedule for the repairs sets construction to begin as early as mid-April and will take approximately 60 days to complete.
The Slabtown Road bridge over U.S. 30 was extensively damaged on Dec. 22 by an over-height vehicle. Slabtown Road was closed immediately. The next day, U.S. 30 westbound was closed to remove a section of the damaged deck and the steel beam to ensure the safety of motorists traveling under the bridge.
The repairs for the Slabtown Road overhead will include removing and replacing all the bridge deck over the westbound portion of U.S. 30. The section of damaged beam that has already been removed will be replaced. One other steel beam will need heat-straightening.
Timetable depends on several factors
The start date for the repairs hinges on how quickly the replacement beam can be custom-fabricated. The timetable for this special order depends on several factors and it could take a couple of months for the beam to be delivered.
“We are doing everything possible to avoid unnecessary delays,” said ODOT District 1 Deputy Director Chris Hughes. “Everyone involved is prioritizing this repair project to avoid having Slabtown Road closed while Thayer Road, Mayberry Road, and Cool Road on U.S. 30 are also closed for another project. If the project closures were to overlap, the local detours would be cumbersome, especially for farmers," said Hughes.
In mid-summer, ODOT will begin a project to construct a restricted crossing U-turn (RCUT) at Thayer Road, and cul-de-sacs at Mayberry Road and Cool Road.
Contingency plans are being considered in the case that Slabtown Road cannot be reopened before the RCUT project begins. One option ODOT is considering is to keep Mayberry Road open at U.S. 30 until the Slabtown Road overhead is reopened.
Prior to the crash, the bridge was in good condition and no upcoming maintenance work was planned for the bridge.
Stories Posted This Week
Monday, September 21, 2026
Sunday, September 20, 2026
- Charmaine M. Spradlin, 74, worked for Associated Plastics
- Bulldog boys soccer win vs. Old Fort
- How Dillinger robbed a Bluffton bank
- Ada School Board recap: School fees waiver estimate is $57K, intervention and after-school program report
- Ada Barnyard Farmers results from 2026 Hardin County Junior Fair
- Rodeheffer awarded Choice One Engineering scholarship
Saturday, September 19, 2026
- Bulldog golf 3rd at final BVC tourney, 2nd overall
- Bulldog football win vs. Perry
- N. Main St. arrest and drug seizure on August 18
- Christian Nationalism poses problems for American democracy
- Weekend Doctor: When should you see an endocrinologist?
- Letter: Background regarding public meeting on data center moratorium
Friday, September 18, 2026
Thursday, September 17, 2026
- Bluffton Icon headlines, September 17
- Bulldog girls soccer 0-0 tie vs. Riverdale
- Bulldog boys soccer loss vs. Riverdale
- Roundhead poet publishes third book
- Bulldog volleyball wins in four vs. Riverdale
- Sept. 15 Ada Council: Impact of big ticket pool repair, public urination ban goes into effect
- Hall named 2026 OMLA Regional Administrative Assistant of the Year
- Play Bingo with Officer Penny at the Ada Public Library
- Adult Book Group books available at APL
- Ada Schools exceed state standards on 2025-2026 Ohio Report Card
- Oct. 6 ONU Trike-A-Thon will raise funds for St. Jude's
- Antibiotic resistance: More to learn