Weather expected to impact Sept. 27 street paving
The Village of Ada has announced that the Street Maintenance Project schedule is weather dependent. For Friday, Sept. 27, pavers will continue working in Ada as able, starting on South Park Drive.
If work is delayed by rain, two paving crews will work on Saturday. One crew would work on Pebble court (finish coat), and then move to north Johnson. The other crew will work in the downtown alleys.
Completed to date: Oak Street, Lehr, Ballard.
Remaining paving: South Park, Downtown alleys, North Johnson.
From the Village: "Thanks for your cooperation and understanding through the project construction."
Stories Posted This Week
Monday, July 28, 2025
Saturday, July 26, 2025
Friday, July 25, 2025
- Special board of education meeting on July 29
- SR81 at Thayer roundabout construction, bridge replacement
- Sondra May Amstutz worked for Airfoil Textron and Midbus
- Jeffrey A. Hunt taught and coached at area schools
- Larry J. Marsh worked for Precision Strip
- Minutes of July 21 Liberty Twp. Park District public meeting
- Old Route 69 Brewery to open on August 1
- Freed Center subscriptions available August 4