U.S. 30 Slabtown bridge estimated to take 60 days to repair
The Ohio Department of Transportation (ODOT) and the Allen County Engineer's Office have completed the initial scope for the repair of the Slabtown Road bridge over U.S. 30, which closed in December due to a bridge strike.
The tentative schedule for the repairs sets construction to begin as early as mid-April and will take approximately 60 days to complete.
The Slabtown Road bridge over U.S. 30 was extensively damaged on Dec. 22 by an over-height vehicle. Slabtown Road was closed immediately. The next day, U.S. 30 westbound was closed to remove a section of the damaged deck and the steel beam to ensure the safety of motorists traveling under the bridge.
The repairs for the Slabtown Road overhead will include removing and replacing all the bridge deck over the westbound portion of U.S. 30. The section of damaged beam that has already been removed will be replaced. One other steel beam will need heat-straightening.
Timetable depends on several factors
The start date for the repairs hinges on how quickly the replacement beam can be custom-fabricated. The timetable for this special order depends on several factors and it could take a couple of months for the beam to be delivered.
“We are doing everything possible to avoid unnecessary delays,” said ODOT District 1 Deputy Director Chris Hughes. “Everyone involved is prioritizing this repair project to avoid having Slabtown Road closed while Thayer Road, Mayberry Road, and Cool Road on U.S. 30 are also closed for another project. If the project closures were to overlap, the local detours would be cumbersome, especially for farmers," said Hughes.
In mid-summer, ODOT will begin a project to construct a restricted crossing U-turn (RCUT) at Thayer Road, and cul-de-sacs at Mayberry Road and Cool Road.
Contingency plans are being considered in the case that Slabtown Road cannot be reopened before the RCUT project begins. One option ODOT is considering is to keep Mayberry Road open at U.S. 30 until the Slabtown Road overhead is reopened.
Prior to the crash, the bridge was in good condition and no upcoming maintenance work was planned for the bridge.
Stories Posted This Week
Friday, November 6, 2026
- Scouting for Food pickup on Saturday, Nov. 7
- Annie's Project in Hardin County, February-March 2027 workshop
- Obituary for Michelle D. Davis, 55
- Down Memory Lane: Fire consumes Administration/Hill Memorial building
- Making corn while the sun shines
- Murder trial postponed in Hardin County Court
- Smith updates Red Men in Red Square
Thursday, November 5, 2026
Wednesday, November 4, 2026
- Jean Ann Sanderson Stager, 97, was an educator
- Barricaded subject incident on TR 180 on November 3
- Apollo Career Center Honor Roll for 1st quarter, 2026-2027
- Ada Schools honor roll for 1st quarter of 2026-2027
- Village of Forest approved for $954K loan for wastewater treatment improvements
- Unofficial results: Ada and Liberty Twp. levy renewals pass
- Community invited to choose BBBS Bowl for Kids’ Sake theme
Tuesday, November 3, 2026
Monday, November 2, 2026
- Bluffton Icon headlines, November 2
- Spencer L. Hall, 39, worked for 5-C Roofing
- Polar Bears sports roundup, October 26 - November 1
- Save December 12 for Merry on Main
- Check out APL events calendar for November 2026
- ICYMI: October 2026 Ada Icon Highlights
- Patrol provides defensive driving tips for high deer crash period